Scheduling a Replacement Date - Screens

As per Select by Single, Multiple or Panel - Screens, choose Single Select, Multi Select or Screen Panel and select the relevant panels. Within the Planning section select either the Replace Schedule or Rotate Schedule buttons.
Screen_Schedule_Replace_1.jpg
For Replace Schedule, choose the Actual Shut and Reason for Replacement, add the Scheduled Change Out Date and a Comment if required. The date defaults to the current date. Select the Tick to save. A photo can also be added here by clicking on the paperclip icon. 

Screen_Schedule_Replace_2.jpg

For Rotate Schedule, choose the Scheduled Shut if required and Scheduled Change Out Date. The date defaults to the current date. Select the Tick to save.

Screen_Schedule_Replace_3.jpg

These will now appear shaded red in the Planning view if scheduled within the next 30 days, or dark grey if scheduled greater than 30 days.

 

 