As per Select by Single, Multiple or Panel - Screens, choose Single Select, Multi Select or Screen Panel and select the relevant panels. Within the Planning section select either the Replace Schedule or Rotate Schedule buttons.
For Replace Schedule, choose the Actual Shut and Reason for Replacement, add the Scheduled Change Out Date and a Comment if required. The date defaults to the current date. Select the Tick to save. A photo can also be added here by clicking on the paperclip icon.
For Rotate Schedule, choose the Scheduled Shut if required and Scheduled Change Out Date. The date defaults to the current date. Select the Tick to save.
These will now appear shaded red in the Planning view if scheduled within the next 30 days, or dark grey if scheduled greater than 30 days.